Pagpapasya sa Jurisdiction ng CIAC: Kailan Maaaring Magpasakop ang mga Hindi Direktang Partido sa Kontrata ng Konstruksyon
G.R. No. 214743, December 04, 2023
INTRODUKSYON
Madalas nating naririnig ang kasabihang, “Ang kontrata ay batas sa pagitan ng mga partido.” Ngunit paano kung mayroong mga third party na sangkot sa kontrata? Maaari ba silang maging responsable o magkaroon ng karapatan dito? Sa larangan ng konstruksyon, kung saan madalas na maraming partido ang sangkot, mahalagang malaman kung sino ang maaaring magpasakop sa isang arbitration clause, kahit na hindi sila direktang partido sa kontrata.
Sa kasong ito, ang isyu ay kung ang Construction Industry Arbitration Commission (CIAC) ay may jurisdiction sa isang dispute sa pagitan ng Hyundai at National Grid Corporation of the Philippines (NGCP), kahit na ang NGCP ay hindi direktang partido sa kontrata ng konstruksyon. Ang kaso ay nagpapakita kung paano ang isang third party ay maaaring magpasakop sa arbitration clause sa isang kontrata ng konstruksyon batay sa kanilang koneksyon sa kontrata at sa uri ng dispute.
LEGAL NA KONTEKSTO
Ang CIAC ay may orihinal at eksklusibong jurisdiction sa mga dispute na nagmumula sa o konektado sa mga kontrata sa konstruksyon sa Pilipinas. Ito ay nakasaad sa Section 4 ng Executive Order No. 1008, na kilala rin bilang Construction Industry Arbitration Law.
Ayon sa Section 35 ng Republic Act No. 9285 (Alternative Dispute Resolution Act of 2004), saklaw ng CIAC ang mga dispute sa pagitan ng mga partido na direktang kasama sa arbitration agreement, o kaya’y obligado rito, direkta man o sa pamamagitan ng reference. Kabilang dito ang project owner, contractor, subcontractor, fabricator, project manager, at iba pa.
Ang Article 1311 ng Civil Code ay nagsasaad na ang mga kontrata ay may bisa lamang sa pagitan ng mga partido, kanilang mga assign, at tagapagmana. Ngunit may mga pagkakataon kung saan ang isang third party ay maaaring maging responsable o magkaroon ng karapatan sa isang kontrata.
PAGLALAHAD NG KASO
Ang Hyundai at TransCo (National Transmission Corporation) ay pumasok sa isang kontrata para sa konstruksyon ng Maramag-Bunawan Transmission Backbone Project. Sa kasagsagan ng implementasyon ng kontrata, pumasok ang TransCo at Power Sector Assets and Liabilities Management Corporation (PSALM) sa isang Concession Agreement kasama ang NGCP, kung saan inako ng NGCP ang mga karapatan at obligasyon ng TransCo sa mga kontrata nito.
Nang magkaroon ng dispute sa pagitan ng Hyundai at NGCP tungkol sa liquidated damages, nagsampa ang Hyundai ng Request for Arbitration sa CIAC laban sa NGCP at TransCo. Kinuwestiyon ng NGCP ang jurisdiction ng CIAC, dahil hindi naman daw sila partido sa kontrata ng konstruksyon.
Ang Court of Appeals (CA) ay pumabor sa NGCP, ngunit binaliktad ito ng Korte Suprema. Ayon sa Korte Suprema, may jurisdiction ang CIAC sa dispute dahil ang NGCP ay itinuturing na assignee ng TransCo sa kontrata ng konstruksyon. Ang NGCP ay may “significant and substantial connection” sa kontrata, kaya’t obligado itong sumunod sa arbitration clause.
SUSING PUNTOS SA DESISYON NG KORTE SUPREMA:
- Ang NGCP ay hindi lamang isang construction manager, kundi isang transferee ng mga karapatan at obligasyon ng TransCo sa ilalim ng Concession Agreement.
- Ang Concession Agreement at Construction Management Agreement (CMA) ay may “significant and substantial connection” sa kontrata ng konstruksyon.
- Ang Section 35 ng R.A. No. 9285 ay nagpapalawak ng jurisdiction ng CIAC sa mga hindi direktang partido sa kontrata ng konstruksyon.
- “When NGCP agreed to the terms of the Concession Agreement, particularly the provisions which bound it to discharge all of TransCo’s obligations under the Transferred Contracts, this necessarily included an agreement to submit to arbitration as provided in the arbitral clause of Construction Contract.”
- “Precisely because NGCP is the transferee of all of TransCo’s rights and obligations under the Construction Contract and because NGCP contractually obligated itself to perform all of TransCo’s contractual obligations thereunder, it is necessarily bound by the arbitration clause.”
- “As a representative of the project owner in the implementation of a construction contract, a construction manager who performed acts for which it could be directly held liable under the construction contract and which would give rise to a construction dispute cannot refuse arbitration simply because it did not sign the arbitration agreement for the inclusion of an arbitration clause in the construction contract.”
PRAKTIKAL NA IMPLIKASYON
Ang desisyon na ito ay nagpapakita na ang arbitration clause sa isang kontrata ng konstruksyon ay maaaring magbuklod hindi lamang sa mga direktang partido, kundi pati na rin sa mga third party na may “significant and substantial connection” sa kontrata. Ito ay mahalaga para sa mga negosyo at indibidwal na sangkot sa industriya ng konstruksyon na maging maingat sa kanilang mga kasunduan at tiyakin na nauunawaan nila ang kanilang mga karapatan at obligasyon.
KEY LESSONS
- Ang mga third party ay maaaring magpasakop sa arbitration clause kung sila ay may “significant and substantial connection” sa kontrata.
- Ang Concession Agreement at CMA ay maaaring maging batayan para sa jurisdiction ng CIAC sa mga hindi direktang partido.
- Ang Section 35 ng R.A. No. 9285 ay nagpapalawak ng jurisdiction ng CIAC sa mga hindi direktang partido sa kontrata ng konstruksyon.
FREQUENTLY ASKED QUESTIONS
1. Ano ang CIAC?
Ang Construction Industry Arbitration Commission (CIAC) ay isang quasi-judicial body na may orihinal at eksklusibong jurisdiction sa mga dispute na nagmumula sa o konektado sa mga kontrata sa konstruksyon sa Pilipinas.
2. Sino ang maaaring magpasakop sa arbitration clause sa isang kontrata ng konstruksyon?
Hindi lamang ang mga direktang partido sa kontrata, kundi pati na rin ang mga third party na may “significant and substantial connection” sa kontrata.
3. Ano ang ibig sabihin ng “significant and substantial connection”?
Ito ay tumutukoy sa isang malapit na relasyon sa pagitan ng third party at ng kontrata ng konstruksyon, tulad ng pagiging assignee, transferee, o construction manager.
4. Paano kung hindi ako sang-ayon sa arbitration?
Kung ikaw ay hindi sang-ayon sa arbitration, maaari kang maghain ng motion to dismiss sa CIAC. Ngunit kung ang CIAC ay magpasya na mayroon silang jurisdiction, kailangan mong sumunod sa arbitration proceedings.
5. Ano ang dapat kong gawin kung ako ay sangkot sa isang dispute sa konstruksyon?
Mahalagang kumunsulta sa isang abogado na may karanasan sa construction law upang malaman ang iyong mga karapatan at obligasyon.
Dalubhasa ang ASG Law sa mga usaping may kinalaman sa construction law. Kung mayroon kang katanungan o nangangailangan ng legal na payo, huwag mag-atubiling makipag-ugnayan sa amin. Maaari kang magpadala ng email sa hello@asglawpartners.com o bisitahin ang aming website sa Contact Us para sa konsultasyon. Kami sa ASG Law ay handang tumulong sa iyo!